5D Cashflow Control: Bid vs Actuals vs PM Forecast vs Projections

How the 2D–5D dimensions stack on the model of record, and why 5D means a live cashflow comparison of Bid Estimate, Actuals, PM Forecast, and system-generated projections.

What the dimensions actually mean

In heavy civil and infrastructure delivery, the dimensions stack onto the model of record. There is no serious "1D" layer — the value starts at the drawings:

  • 2D — drawings, plans, areas, sheets, profiles, sections, and takeoff surfaces.
  • 3D — real geometry, model elements, quantities, spatial relationships, and constructability.
  • 4D — time-based simulation with schedule, sequencing, planned vs actual progress, and production logic.
  • 5D — cashflow projection with a live comparison of Bid Estimate vs Actuals vs PM Forecast vs system-generated projections.

5D is where project controls becomes intelligence. Once cost and revenue are bound to geometry, quantities, and the schedule, you can answer the questions executives actually ask: Are we ahead or behind? Will we finish on budget? When will we need cash?

The four-way comparison

5D forecasting is most useful when these four curves are compared on the same axis:

ViewWhat it isOwner
Bid EstimateThe baseline cost/revenue from the winning bidEstimating
ActualsCommitted and incurred cost + billed revenue to dateAccounting / ERP
PM ForecastThe project manager's judgment of cost at completionProject controls
System ProjectionArtemis's data-driven projection from production trendsArtemis

Supporting earned-value metrics — CPI (earned ÷ actual), SPI (earned ÷ planned), and EAC (estimate at completion) — explain why the curves diverge.

Why cashflow is the real output

Profit is an opinion; cash is a fact. A 5D model projects monthly cashflow by combining the schedule-loaded cost and revenue with payment terms and retention. That is what keeps a project solvent — and what most teams compute far too late.

How Artemis automates it

  1. Ingest schedule, cost, and billing artifacts (P6, Excel, ERP / CMiC).
  2. Bind cost and revenue to quantities, activities, and scope — flagging gaps.
  3. Forecast cashflow and compare Bid vs Actuals vs PM Forecast vs system projection, with an auditable trail back to source.
  4. Report an executive narrative and the recommended action on demand.